Approval Steps
Step 1: Submit to Buildpro
Plans are submitted to our dedicated web portal, LWP BuildPro. Most builders are already registered. If your company doesn’t appear in the drop-down menu email your company name, contact number and contact email to huntlee@lwpproperty.com.au and we will set you up in the system.
Submit a surveyed site plan, floor plan(s), elevations, sections and external colours and materials schedule to BuildPro. LWP will provide stamped approved plans if the design complies, or feedback and marked-up plans if amendments are required, within ten working days.
Step 2: Altogether Group (water and sewer) Approval
Read the requirements in the Building & Developing section of the Altogether website: Altogether Group documentation can be found here.
Set up an Altogether account via their website.
Submit your water services plan, site/landscape plan and BASIX certificate to Altogether via their website. Allow ten working days for approval.
Step 3: Provide Altogether approval to Buildpro
Once you receive Altogether Group approval, upload the approved documents to the LWP BuildPro portal for developer full design approval.
Step 4: Council Approval
Submit developer approved plans to Council and/or relevant authorities to seek construction approval.